SBI PO – 2015 – 08

Question:  A and B can do a piece of work in 12 days, B and C in 15 days, C and A in 20 days. In how many days can all of A, B and C together finish the whole work? [Ans. (a) 10 days]

(a)  20 days     (b) 10 days     (c) 5 days      (d) 12 days     (e) None of these