Question: To do a certain work B would take three
times as long as A and C together and C twice as long as A and B together. The
three men together complete the work in 10 days. How long would A take to
complete the work alone? [Ans. (c) 24
days]
(a) 25 days (b)
30 days (c) 24 days (d) 40 days
(e) None of these
Solution:
Detailed Explanation:
Given that, to do a certain work B would take three times as long
as A and C together. So, 3B=A+C.
So, A+B+C= (A+C)
+B=3B+B=4B
Given that the three men A, B and C together can complete
the whole work in 10 days. So, 4B can complete the work is 10 days. Therefore,
B alone can complete the entire work is 40 days.
Also, since C takes twice the time than that of A and
B together. So, 2C=A+B
So, (A+B)+C=2C+C=3C
Thus, 3C can complete the work is 10 days. Therefore, C
alone can complete the entire work is 30 days.
Since the three men A, B and C together can complete
the whole work in 10 days.
Therefore, A’s one day work = [(1/10) – {(1/40) + (1/30)}]
= 1/24
So, A alone can do the work is 24 days. Ans.
Solution:
3B=A+C and 2C=A+B
A+B+C=4B ≡10
days, so B≡40 days
A+B+C=3C ≡10 days, so C≡30 days
A=
– [
+
] =
,
So, A=24 days Ans.
No comments:
Post a Comment